This sidewalk had a manhole sewer outlet that had crumbled from deterioration and traffic wear. The loosen material is being removed and the area cleaned. |
In this instance due to time because of the location Steel Grip Minute Cement was used. Feather out to zero and a coat of Steel Grips Liquid Concrete completed the work. Total time for this particular job one hour. |
For small jobs such as the following pictures show, use the M1000 dry-pack directions and mix in a wheel barrow. Click on mixing directions. |
Use the M1000 pre-mix (click mixing directions) on the repair area usually a brush is used. Then place M1000 dry-pack (click mixing direction) in repair area. Using two trowels pack and form to the exsisting sidewalk. The firmer you pack the material the stronger the repair. |
Continued placement photo |
Continued placment photo |
Continued placment photo. |
Job is completed with a final brushing/roller of M1000 concrete slurry (click on mixing instructions). |
This photo shows a large piece of sidewalk missing. Here you will use the M1000 pre-mix, M1000 dry pack, M1000 concrete slurry and a bendaboard. |
Use the bend-a-board as a form. Wet repair area with M1000 pre-mix. Place M1000 dry pack and smooth out with trowels. |
The work is troweled and then receives a brush/rolled finish with a coat of M1000 concrete slurry. Work time 10 minutes. |
This is a rock curb that had been damaged and set for repair. Material is M1000 dry-pac and pre-mix. |
Wet area with M1000 pre-mix. Spread M1000 dry pack on repair area. |
Smooth out M1000 dry-pac with a couple of hand trowels. Press hard. |
Continued placement. |
Un-finished placement. |
Then re-form the rock outlines and smooth out the rocks. |
Continue making rock outlines. |
The work is now completed resembling the rock curb. A coat of pre-mix is applied to the finished job. |
Sidewalk has a large portion that has deteriorated leaving a large hole. M1000 pre-mix is first applied. |
Fill the hole with M1000 dry-pack. |
Sprinkle M1000 pre-mix on top of the dry-pack and trowel out to a smooth finish feathering out to zero. Work Time 10 minutes. |
This sidewalk had lifted. The area was sprinkled with M1000 pre-mix and the M1000 dry-pack applied. |
After troweling the dry-pack, then a brushing of M1000 pre-mix is used for a non-skid surface and to assist in finishing the work to a zero edge. |
Continued completion. |
Work is barricaded until dry in about 4-5 hours. Total worktime approximately 15-20 minutes. |
A low area in street run off that causes pedestrian to be splashed is being prepared for a Steel Grip quick repair. The area is treated with M1000 pre-mix. |
On top of the pre-mix the M1000 concrete mix is applied and trowelled into place. |
The concrete is then broomed for a non skid surface. |
Work completion time was one half hour. The work is then barricaded to allow drying. |
This floor is the U.S. Olympic Stadium. Steel Grip was asked to provide a non-slip durable surface. To this date the floor still has the appearance of brand new. |
Disneyland concourse is now complete for pedistrian traffic. |
As previously shown the pedestrian concourse at Disneyland was completed by Steel Grip. |